The company, the land, the licences and the progress

The registered company and its capital, completed projects you can drive to, the chanote type and mortgage status, the allocation licence, the EIA threshold, the 2011 flood line, and a dated progress table.

Ruensuan Property Co., Ltd.

Registered
2013 (13 years)
Company registration no.
0105556XXXXXX — fictional; a real Thai company number is 13 digits starting 0-1-05 for a Bangkok Co., Ltd.
Paid-up capital
฿150,000,000
Business
Detached-house land allocations in Pathum Thani and the northern Bangkok periphery only. No condominiums, no off-plan high-rise, no land banking for resale.

The site names the company and its registration, not people.

Completed projects — you can drive to these

ProjectDistrictCompletedHomesJuristic handover
Ruensuan Khlong 2Lam Luk Ka, Pathum Thani2015342017
Ruensuan Mueang PathumMueang Pathum Thani2017482019
Ruensuan Rangsit–Khlong 6Thanyaburi, Pathum Thani2020292022
Ruensuan Lam Luk Ka Khlong 3Lam Luk Ka, Pathum Thani2023402025
Ruensuan Lam Luk Ka Khlong 4(this project)Lam Luk Ka, Pathum Thani2025 / 202722

This project is the company's first single-storey-only, lowest-density line. The prior four are conventional 1–2 storey projects at 7–10 homes/rai — this site says so; it does not pretend the company only ever built like this.

The land

Title
Chanote (โฉนด, น.ส. 4 จ.), parent deed Pathum Thani No. 4XXXX (fictional), being subdivided into 22 plot chanotes under the allocation
Encumbrance
The parent land is mortgaged to [Bank] เพื่อการพัฒนาโครงการ (project finance). Each plot’s chanote is released from the mortgage (ปลอดภาระจำนอง) at the Land Office on the day it transfers to the buyer — the company releases it against the bank’s payment from the sale proceeds. The buyer receives the หนังสือปลอดจำนอง at transfer. A sample release clause is reproduced on this page.
Land allocation licence
ใบอนุญาตให้ทำการจัดสรรที่ดิน No. XX/2567 (fictional), issued by the Pathum Thani Land Allocation Committee. What it obliges: the developer must build the approved road, drainage, lighting and common utilities and maintain them until the juristic person takes over; the common area cannot be sold; the plots cannot be transferred to buyers until the common infrastructure is accepted.
Construction permit
ใบอนุญาตก่อสร้าง (แบบ อ.1) per house, issued by เทศบาลเมืองลำลูกกา
EIA
Housing projects need an EIA at ≥ 80 units or ≥ 4 rai combined building area, or ≥ 500 units. This project (22 units) is below the threshold — no EIA is required or filed. The site says so, and lists what the developer did voluntarily on drainage instead of leaving the sentence there.
Escrow
Optional under the พ.ร.บ. การดูแลผลประโยชน์ของคู่สัญญา พ.ศ. 2551. The buyer may elect an escrow account for the pre-transfer payments; the escrow fee (~0.1–0.3% of contract value, split by agreement) is the buyer’s. The developer does not require it and does not discount for waiving it.

Closing costs — who pays what

ItemRatePaid by
Transfer fee2% of appraised value — currently reduced to 0.01% for homes ≤ ฿7M under the government measure to 31 Dec 2026 (real measure; verify the date at deploy)split 50 / 50
Mortgage registration fee1% of the loan amount — currently reduced to 0.01% under the same measurebuyer (if financing)
Specific Business Tax + local tax3.3% of the higher of price / appraiseddeveloper
Withholding taxprogressive, on appraised valuedeveloper
Stamp duty0.5% — not charged when SBT appliesdeveloper
Utility meter connection (water + electricity)฿18,500 fixed (fictional)buyer
Common-area sinking fund (one-off)฿550 / sq wahbuyer

Worked example — Plot 11, ฿5,036,000, 80% loan: the buyer pays ≈ ฿76,400 at transfer (≈ ฿148,000 at the normal rates).At the normal 2% / 1% rates this line would be ≈ ฿148,000 — both figures are shown on the site. Bank and legal fees the bank sets are on top.

Flood & drainage — the local point

2011
The 2011 central-Thailand flood reached ~0.9 m above the then road level at this location (fictional site figure). Lam Luk Ka Khlong 4 was inundated for ~4 weeks.
Finished floor level
+1.20 m above the project road crown
Project road crown
+0.80 m above the existing khlong-side ground level — so finished floor sits ~2.0 m above pre-development ground, ~1.1 m above the 2011 line
On-site retention
A 1,900 m³ retention pond + 2 pumps (1 duty, 1 standby, auto changeover) discharging to Khlong 4 at a controlled rate agreed with the ชลประทาน.

The site does not claim the project cannot flood; it publishes the levels and the 2011 reference and lets the buyer’s surveyor judge.

Pre-development ground2011 flood lineProject road crownFinished floor level+2.00 m+0.90 m0.00 m (datum)
Photograph: the soi off Liap Khlong 4 road at the project entrance — the khlong, the road, the drainage works, honest and unstaged.

Build progress — as of 31 August 2026

a snapshot, not a live feed

Phase 1 (12 homes)
Complete; 9 transferred, 3 available
Phase 2 (10 homes)
Structure complete on 6, roofing on 4; target handover Q2 2027
Common road & drainage
85% — final wearing course pending Phase 2 completion
Retention pond & pumps
Complete and commissioned
Entrance gatehouse
Complete
Show home
House 3 (Type B), open daily 09:00–17:00